 Site Plan & Permit Approval Timelines
Print Page Save Link

Major Site Plan Approval - Time Lines - No resubmittals needed

SUBMITTAL TASK MAX TIME LINE
Developer submits application Sufficiency Review 2 days
  Data entry and submittal to reviewers 1 day
  Development Review Staff (DRS) reviews site plan 10 days
  Site plan signed by all required divisions/department staff 2 days
  Zoning clearance issued 1 day
Total 16 days

Major Site Plan Approval - Time Lines - One Resubmittal needed

SUBMITTAL TASK MAX TIME LINE
Developer submits application Sufficiency Review 2 days
  Data entry and submittal to reviewers 1 day
  Development Review Staff (DRS) reviews site plan 10 days
  More items/documents needed, comments letter sent 2 days*
Developer resubmits items Sufficiency Review 1 day
  Data entry and submittal to reviewers 1 day
  DRS reviews resubmittal information 5 days (if not sufficient, start at *).
  Site plan signed by all required divisions/department staff 2 days
  Zoning clearance issued 1 day
Total 25 days
Note: Each resubmittal adds 9 days to the approval time.

Minor Site Plan Approval - Time Lines - No resubmittals needed

SUBMITTAL TASK MAX TIME LINE
Developer submits application Sufficiency Review and data entry 2 days
  Development Review Staff (DRS) reviews site plan 5 days
  Site plan signed by all required divisions/department staff and zoning clearance issued 1 day
Total 8 days

Minor Site Plan Approval – Time Lines – One Resubmittal needed

SUBMITTAL TASK MAX TIME LINE
Developer submits application Sufficiency Review and data entry 2 days
  Development Review Staff (DRS) reviews site plan 5 days
  More items/documents needed, comments letter sent 1 day *
Developer resubmits items Sufficiency Review and data entry 2 day
  DRS reviews resubmittal information 5 days (if not sufficient, start at *).
  Site plan signed by all required divisions/department staff and zoning clearance issued 1 day
Total 16 days
Note: Each resubmittal adds 8 days to the approval time.

Major and Minor Commercial Building Permit - Time Lines - No resubmittal needed

SUBMITTAL TASK MAX TIME LINE
Contractor submits permit application Plans reviewed and permit issued 10 days
Total 10 days

Major and Minor Commercial Building Permit - Time Lines - One resubmittal needed

SUBMITTAL TASK MAX TIME LINE
Contractor submits permit application Plans reviewed and comments letter sent 10 days
Contractor resubmits documents/corrections Resubmittal documents scanned 1 day *
  Plans reviewed and permit issued 5 days (if not sufficient, start at * ).
Total 16 days
Note: Each resubmittal adds 6 days to the approval time.